Table Of ContentThe Contractor’s NEC3 ECC Handbook
The Contractor’s NEC3 ECC Handbook
Steven C. Evans
This edition first published 2017
© 2017 John Wiley & Sons Ltd
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or
transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise,
except as permitted by law. Advice on how to obtain permission to reuse material from this title is available
at http://www.wiley.com/go/permissions.
The right of Steven C. Evans to be identified as the author of this work has been asserted in accordance
with law.
Registered Offices
John Wiley & Sons, Inc., 111 River Street, Hoboken, NJ 07030, USA
John Wiley & Sons Ltd, The Atrium, Southern Gate, Chichester, West Sussex, PO19 8SQ, UK
Editorial Office
9600 Garsington Road, Oxford, OX4 2DQ, UK
For details of our global editorial offices, customer services, and more information about Wiley products
visit us at www.wiley.com.
Wiley also publishes its books in a variety of electronic formats and by print‐on‐demand. Some content that
appears in standard print versions of this book may not be available in other formats.
Limit of Liability/Disclaimer of Warranty
While the publisher and authors have used their best efforts in preparing this work, they make no
representations or warranties with respect to the accuracy or completeness of the contents of this work and
specifically disclaim all warranties, including without limitation any implied warranties of merchantability
or fitness for a particular purpose. No warranty may be created or extended by sales representatives, written
sales materials or promotional statements for this work. The fact that an organization, website, or product
is referred to in this work as a citation and/or potential source of further information does not mean that
the publisher and authors endorse the information or services the organization, website, or product may
provide or recommendations it may make. This work is sold with the understanding that the publisher is not
engaged in rendering professional services. The advice and strategies contained herein may not be suitable
for your situation. You should consult with a specialist where appropriate. Further, readers should be aware
that websites listed in this work may have changed or disappeared between when this work was written
and when it is read. Neither the publisher nor authors shall be liable for any loss of profit or any other
commercial damages, including but not limited to special, incidental, consequential, or other damages.
Library of Congress Cataloging‐in‐Publication data applied for
ISBN: 9781119137498
Cover design by Wiley
Cover images: (Main image) © usssajaeree/Gettyimages;
(Background image) © James Miller / EyeEm/Gettyimages
Set in 10/12pt Warnock by SPi Global, Pondicherry, India
10 9 8 7 6 5 4 3 2 1
v
Contents
About the Book xiii
About the Author xv
1 Introduction 1
Ten Things You Need to Know 1
Author’s Note 2
2 The Contract 5
About the NEC Contract 5
Clarity and Simplicity 5
Flexibility 5
Stimulus to Good Management 6
Collaborate…or Else! 6
The Latham Report 6
The NEC3 Suite 7
Contracts 7
Flow Charts and Guidance Notes 8
The ECC Form 9
The Core Clauses 9
The Main Options 9
Option A – Priced Contract with Activity Schedule 10
Option B – Priced Contract with Bill of Quantities 11
Option C – Target Contract with Activity Schedule 11
Option D – Target Contract with Bill of Quantities 12
Option E – Cost Reimbursable Contract 12
Option F – Management Contract 13
W Clauses 13
The Secondary Options 14
X Clauses 14
Y Clauses 14
Z Clauses 15
The Contract Data 15
The Schedules 16
The Schedule of Cost Components 16
The Shorter Schedule of Cost Components 16
vi Contents
Formation of the Contract 16
Offer and Acceptance 16
Attestation 17
Necessary Contract Documents 17
Frequently Asked Questions 17
3 General 19
Overview 19
Actions 19
The Employer 20
The Contractor 22
The Project Manager 27
Impartiality 32
The Supervisor 32
The Obligations 33
Identified and Defined Terms 34
(1) The Accepted Programme 35
(2) Completion 36
(3) Completion Date 38
(4) The Contract Date 38
(5) Defect 39
(6) Defects Certificate 39
(7) Equipment 40
(8) The Fee 40
(9) Key Date 41
(10) Others 42
(11) Parties 42
(12) Plant and Materials 42
(13) To Provide the Works 43
(14) The Risk Register 44
(15) The Site 44
(16) Site Information 45
(17) Subcontractor 45
(18) Working Areas 46
(19) Works Information 46
(20) The Activity Schedule (Main Options A and C Only) 49
Who Prepares the List of Activities? 49
What Should be Included in the Schedule? 50
Relationship to the Accepted Programme 50
Changes to the Activity Schedule 50
Use Under Option A 51
Use Under Option C 51
Errors in the Activity Schedule 51
(21) The Bill of Quantities (Main Options B and D Only) 52
Changes to the Bill of Quantities 53
Use Under Option B 53
Use Under Option D 53
Errors in the Bill of Quantities 54
Contents vii
(22) to (26) Defined Cost 54
Main Options A and B 54
Main Options C to E 54
Main Option F 55
(25) Disallowed Costs 55
(27) Price for Work Done to Date (Option A) 56
(28) Price for Work Done to Date (Option B) 56
(29) Price for Work Done to Date (Options C to F) 57
(30) Prices (Main Options A and C) 57
(31) Prices (Main Options B and D) 57
(32) Prices (Main Options E and F) 57
(33) The Total of the Prices (Option D) 57
Interpretation and the Law 57
Communications 58
Notification 59
The Project Manager and the Supervisor 60
Adding to the Working Areas 61
Early Warning 61
Ambiguities and Inconsistencies 63
Illegalities and Impossibilities 64
Prevention 64
Frequently Asked Questions 65
4 The Contractor’s Main Responsibilities 71
Overview 71
Providing the Works 77
The Contractor’s Design 78
Acceptance of the Contractor’s Design 78
Using the Contractor’s Design 79
Design of Equipment 79
People 80
Working With the Employer and Others 81
Subcontracting 82
Other Responsibilities 84
Frequently Asked Questions 85
5 Time 89
Overview 89
Starting, Completion and Key Dates 89
Commencement and Completion 89
Completion Certificate 90
Key Dates 91
The Programme 91
The First Programme 92
Information on the Programme 92
Acceptance of the Programme 95
Rejection of the Programme 95
Revising the Programme 96
viii Contents
Access to and Use of the Site 98
Instructions to Stop or Not to Start the Work 98
Takeover 98
Acceleration 99
Frequently Asked Questions 100
6 Testing and Defects 105
Overview 105
Tests and Inspections 106
Tests and Inspections Before Delivery 107
Searching For and Notifying Defects 107
Searching 107
Notifying 108
Correcting Defects 108
Correction 108
Defect Correction Period 108
Defects Certificate 109
Accepting Defects 109
Uncorrected Defects 110
Frequently Asked Questions 111
7 Payment 115
Overview 115
Assessing the Amount Due 115
Main Option A 116
Main Option B 117
Main Option C 117
Amounts Due to Subcontractors 118
The Cost of Components in the Schedule of Cost Components 119
Disallowed Costs 119
The Fee 120
Main Option D 120
Amounts Due to Subcontractors 121
The Cost of Components in the Schedule of Cost Components 121
Disallowed Costs 121
The Fee 122
Main Option E 122
Amounts Due to Subcontractors 123
The Cost of Components in the Schedule of Cost Components 124
Disallowed Costs 124
The Fee 125
Main Option F 125
Amounts Due to Subcontractors 126
The Prices for the Work Done by the Contractor 127
Disallowed Costs 127
The Fee 127
Contents ix
Unfixed Materials on Site 128
Main Option A 128
Main Option B 128
Main Options C, D and E 128
Main Option F 128
The First Programme 128
Payment 128
The Primary Legislation 129
The Secondary Legislation 129
How it Works 129
A ‘Construction Contract’ 129
The Payment Provisions 130
The Payment Notice 130
The ECC Provisions 131
Interest 132
Defined Cost 132
The Contractor’s Share 133
The Activity Schedule 134
The Bill of Quantities 135
Frequently Asked Questions 135
8 Compensation Events 139
Overview 139
Compensation Events 140
Core Clause Compensation Events 140
Weather Measurement 146
Weather Data 146
Once in Ten Years 146
Bill of Quantity Compensation Events 149
Secondary Option Compensation Events 150
Clause X2.1 – Changes in the Law 150
Clause X12.3(6) and (7) – Changes in Partnering Information 151
Clause X14.2 – Delay in Making Advanced Payment 151
Clause X15.2 – Correction of a Defect 151
Clause Y2.4 – Suspension Under the Housing Grants,
Construction and Regeneration Act 1996 151
Compensation Event Procedure 151
Notifying Compensation Events 151
Quotations for Compensation Events 154
Assessing Compensation Events 156
Effect of the Event on Defined Cost 157
Effect of the Event on Planned Completion 158
Failure to Give Early Warning 159
The Project Manager’s Assessment 159
Exhaustive Remedy 161
Implementing Compensation Events 161
x Contents
Main Option Clauses 161
Summary of Sanctions 163
Other Remedies 164
Frequently Asked Questions 164
9 Title 169
Overview 169
The Employer’s Title to Plant and Materials 169
Marking Equipment, Plant and Materials Outside the
Working Areas 170
Removing Equipment 171
Objects and Materials within the Site 171
Frequently Asked Questions 171
10 Risks and Insurance 173
Overview 173
Employer’s Risks 173
Contractor’s Risks 174
Repairs 175
Indemnity 175
Insurance Cover 175
Insurance Policies 176
If the Contractor Does Not Insure 176
Insurance by the Employer 177
Frequently Asked Questions 177
11 Termination 179
Overview 179
Termination 179
Reasons for Termination 180
Procedures on Termination 181
Payment on Termination 181
Frequently Asked Questions 183
12 Dispute Resolution (W1 and W2 Adjudication) 185
Overview 185
Option W1 185
Dispute Resolution 185
The Adjudicator 186
The Adjudication 188
Review by a Tribunal 191
Option W2 192
Dispute Resolution 192
The Adjudicator 193
The Adjudication 196
Review by a Tribunal 199
Frequently Asked Questions 200
Contents xi
13 X and Y Clauses 203
Introduction 203
The X Clauses 203
X1 – Price Adjustment for Inflation 203
X2 – Changes in the Law 204
X3 – Multiple Currencies 204
X4 – Parent Company Guarantees 205
X5 – Sectional Completion 205
X6 – Bonus for Early Completion 205
X7 – Delay Damages 206
X12 – Partnering 206
X13 – Performance Bond 207
X14 – Advanced Payment to the Contractor 207
X15 – Limitation of Contractor’s Liability for his Design
to Reasonable Skill and Care 207
X17 – Low Performance Damages 208
X18 – Limitation of Liability 208
X20 – Key Performance Indicators 209
The Y Clauses 209
Y(UK)1 – Project Bank Account 209
Overview 209
Definitions 210
Project Bank Account 210
Named Suppliers 210
Payments 211
Effect of Payment 211
Trust Deed 211
Termination 211
Y(UK)2 – Housing Grants, Construction and Regeneration Act 1996 212
Overview 212
Definitions 212
Dates for Payment 212
Notice of Intention to Pay Less 212
Suspension of Performance 212
Y(UK)3 – Contracts (Rights of Third Parties) Act 1999 213
Overview 213
Frequently Asked Questions 213
14 Z Clauses 215
Overview 215
Additional Conditions of Contract 215
Frequently Asked Questions 216
15 Schedules of Cost Components 219
Overview 219
Schedule of Cost Components 219
Subcontractors 220
Description:Addresses the daily challenges faced by contractors who use the NEC3 ECC with clear, practical and useable advice on how to solve them Written in plain English for contractors and their staff, this book explains how the NEC3 contract works and provides answers to common questions. It presents compli