Table Of ContentBTC PROJECT ESIA
GEORGIA
FINAL ESIA
APPENDIX A
ANNEX I REINSTATEMENT SUMMARY PLAN
TABLE OF CONTENTS
Page No
1 INTRODUCTION 1
2 DOCUMENTATION 2
3 EROSION CLASSES 2
4 SITE CLEAN-UP 3
5 INTERIM REINSTATEMENT OF THE ROW 4
5.1 Land in Erosion Classes 1, 2 and 3 4
5.2 Land in Erosion Classes 4, 5, 6 and 7 (Except Boulder Fields) 4
5.3 Boulder fields 5
5.4 Watercourses 5
6 REINSTATEMENT OF LAND OTHER THAN ROW 5
6.1 Land at construction support facilities 5
6.2 Waste disposal sites 5
6.3 Roads and access tracks 5
7 REINSTATEMENT PROCEDURES 6
7.1 Topsoil removal and storage 6
7.2 Subsoil removal and storage 6
7.3 Trench excavation and pipeline padding 7
7.4 Reinstatement of soils 8
7.4.1 Reinstatement of subsoil 8
7.4.2 Reinstatement of topsoil 8
7.5 Temporary erosion control measures 9
7.5.1 General 9
7.5.2 Erosion matting 9
7.5.3 Sediment control 9
7.5.4 Soil-cuttings control 10
7.6 Permanent erosion control devices 10
7.6.1 Diverter berms 10
7.6.2 Berm outlets 10
7.6.3 Gabions 10
7.6.4 Trench breakers 10
7.7 Watercourses 11
8 BIO-RESTORATION 11
8.1 Objectives 11
8.2 Targets 11
8.3 Scheduling 12
8.4 Procedures for biorestoration 12
9 SPECIAL AREAS 12
10 RESTRICTING ACCESS 13
11 HANDOVER AND POST-CONSTRUCTION MAINTENANCE 13
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
BTC PROJECT ESIA
GEORGIA
FINAL ESIA
TABLES
Table 3-1 Erosion classes 3
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
BTC PROJECT ESIA
GEORGIA
FINAL ESIA
REINSTATEMENT SUMMARY PLAN
1 INTRODUCTION
Reinstatement of project areas disturbed by pipeline construction activities (eg ROW, camps,
pipe yards, etc) to the original landscape character is a specific objective aimed to achieve the
goal of no harm to the environment, and encapsulates benefits that include:
Improved likelihood of maintaining pipeline integrity against inclement conditions and
natural erosion
Natural landscape and it’s tourism resource value are maintained
Soil fertility for both natural and agricultural environments is preserved, and thereby
reduces the risk of desertification is reduced
Water catchments and the associated water quality are protected
Bio-diversity of the global genetic pool is sustained
This plan summarises the specific requirements developed for reinstating areas disturbed by the
project, and takes in to account the anticipated subsequent development of the SCP project.
The standards for reinstatement are current best practice, and have been developed from
international standards and guidelines, and lessons learnt from projects in Europe, Africa, South
America, and the Caucasus.
Issues addressed include topographical reinstatement, erosion control, and bio-restoration; and
requirements for the extraction, re-use and if necessary the disposal of material excavated from
the pipeline trench.
The reinstatement strategy is based on the following principles:
Areas disturbed by pipeline construction activities will be restored to pre-construction
conditions (eg contours) to the greatest extent possible
There will be no adverse impacts on sensitive habitats outside of the ROW as a result of
construction activities, in particular when forming cuts on side slopes
Soils in disturbed areas will be stabilized, using both temporary and permanent controls,
to protect the integrity of the pipeline and minimize potential sediment and erosion
impacts
Topsoil will be handled and stored to retain soil structure, viability of its natural seed
bank, and its fertility
Topsoil and subsoil operations will be carried out in a way which minimizes the risk of
soil loss down slopes and into watercourses
Bio-restoration of disturbed areas will be to conditions similar to the immediately
adjacent off-ROW, and will be undertaken in order to:
(a) restore the ecology existing before construction, particularly the variety and
distribution pattern of plant species, using indigenous flora
(b) establish sufficient vegetative cover to minimise erosion and meet the performance
target of Erosion Class 3 or better through restoration of the local plant community
Surplus excavated material will be disposed of in an environmentally acceptable manner
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
A-I-1
BTC PROJECT ESIA
GEORGIA
FINAL ESIA
Reinstatement activities will be monitored until environmental requirements and goals
will be achieved
2 DOCUMENTATION
A Reinstatement Plan including Method Statements, inspection plans, and record portfolios for
all erosion control and reinstatement works, will be produced by the Contractor for project
approval. The documentation will comply with project, ESIA, pre-entry agreement, and any
other relevant Authorities’ requirements.
The Contractor will make a photographic and or video record of the ROW before opening the
ROW and following final reinstatement.
The construction ?ontractor will prepare method statements for project approval specifically
addressing:
Environmentally Sensitive Areas
Reinstatement of watercourse crossings, including generic methods for all watercourse
crossings and site-specific methods statements for significant or sensitive watercourse
crossings in environmentally sensitive or special agricultural sections
Boulder fields
Temporary and permanent measures to stabilise and control erosion for project affected
areas
Special agricultural areas that support more complex agricultural systems eg canals, and
or irrigation systems
3 EROSION CLASSES
Erosion classes are used as the basis for determining erosion targets for temporary and
permanent reinstatement. Table 3-1 below gives the definition of erosion classes. The aim is to
meet erosion class 3 or better representing moderate erosion.
As a minimum the following standards will be achieved:
Very low risk of the depth of cover above the pipeline being reduced
Very low risk of releasing soil off-site (where there is a risk of sediment significantly
impacting water bodies sediment interception devices will be installed)
Low risk of damage to bio-restoration work through washing-out of seeds and plants
An erosion risk assessment has been undertaken of the route. This assessment identified areas of
potential erosion and assigned erosion control measures for each area of the route.
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
A-I-2
BTC PROJECT ESIA
GEORGIA
FINAL ESIA
Table3-1 Erosion classes
Erosion Verbal Erosion Visual assessment
class assessment rate
(t/ha)
1 Very slight < 2 No evidence of compaction or crusting of the soil.
No wash marks or scour features. No splash
pedestals or exposed roots or channels
2 Slight 2-5 Some crusting of soil surface. Localised wash but
no or minor scouring. Rills (channels <1m2 in
cross-sectional area and < 30cm deep) every 50-
100m. Small splash pedestals where stones or
exposed roots protect underlying soil
3 Moderate 5-10 Wash marks. Discontinuous rills spaced every 20-
50m. Splash pedestals and exposed roots mark
level of former surface. Slight risk of pollution
problems downstream
4 High 10-50 Connected and continuous network of rills every 5-
10m or gullies (> 1m2 in cross-sectional area and
> 30cm deep) spaced every 50-100m. Washing
out of seeds and young plants. Reseeding may be
required.
Danger of pollution and sedimentation problems
downstream
5 Severe 50-100 Continuous network of rills every 2-5m or gullies
every 20m. Access to site becomes difficult.
Revegetation work impaired and remedial
measures required. Damage to roads by erosion
and sedimentation. Siltation of water bodies
6 Very severe 100-500 Continuous network of channels with gullies every
5-10m. Surrounding soil heavily crusted. Integrity
of the pipeline threatened by exposure. Severe
siltation, pollution and eutrophication problems
7 Catastrophic > 500 Extensive network of rills and gullies; large gullies
(> 10m2 in cross-sectional area) every 20m. Most
of original surface washed away exposing pipeline.
Severe damage from erosion and sedimentation
on-site and downstream
4 SITE CLEAN-UP
Prior to demobilization the contractor will clean-up all areas affected by construction operations
after backfilling and before replacement of soil. In other project areas, the contractor will clean-
up immediately on cessation of construction activity. Clean-up includes removal of all plant,
equipment and materials not required for replacement of soil and subsequent bio-restoration.
In pre-developed areas (either for agriculture or industry) the cleaned-up condition will be
equivalent to, or better than, the condition prior to construction.
Waste materials will not be left, or buried or disposed of in any way on any project area, except
for:
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
A-I-3
BTC PROJECT ESIA
GEORGIA
FINAL ESIA
on-site incineration
excess soil and rock
waste disposed of at approved waste disposal sites that will have been selected the
project and that have been approved by the relevant authorities to undertake such
operations
5 INTERIM REINSTATEMENT OF THE ROW
The pipeline construction contractor will reinstate the full width of the BTC ROW as the base
case.
Should the SCP installation follow directly from the BTC pipeline, full reinstatement will only
be carried out on sections that will not be disturbed by SCP construction activities. Interim
reinstatement will be carried out over the remaining portion of the ROW to cover the period
between installation of the two pipelines. If there is a delay of more than 12 months between
carrying out interim reinstatement and the start of SCP construction, the whole of any section
which is subject to potentially severe or very severe erosion will be fully reinstated. Final
reinstatement of the joint land would be the responsibility of the SCP project.
In environmentally sensitive areas the contractor will backfill and reinstate the ROW as far as
practicable, immediately after installation of the pipeline.
Temporary reinstatement procedures will vary depending on the erodability of each particular
area. Some of the specific tools used for interim reinstatement are described in Section 7.5.
The following briefly describes the activities for land in each of the erosion classes in Table 3-1.
5.1 LAND IN EROSION CLASSES 1, 2 AND 3
The erosion risk on land in these classes is low and interim control measures will be limited to
those necessary to maintain class3. After installation of the BTC pipeline, the subsoil will be
replaced in the trench. Topsoil will be stored according to requirements set out in section 7.
Temporary erosion control measures will be installed and functional until the SCP is installed
except in cases as described above.
5.2 LAND IN EROSION CLASSES 4, 5, 6 AND 7 (EXCEPT
BOULDER FIELDS)
The subsoil will be returned to the areas from which it was excavated and compacted while
topsoil will continue to be stored. The land will then be covered with erosion matting and any
other temporary erosion control measures required will be installed.
By the time the SCP is installed, the mat should have deteriorated sufficiently so as to present
no hazard to the following construction operations. Any residue of the mat after the second pipe
is installed will be buried within the subsoil and below the topsoil and will decompose.
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
A-I-4
BTC PROJECT ESIA
GEORGIA
FINAL ESIA
5.3 BOULDER FIELDS
The high density of stones within the boulder fields will generally be sufficient to protect the
land against erosion, so no special measures are envisaged. Method Statements will be produced
by the Contractor to meet erosion control targets.
5.4 WATERCOURSES
Interim reinstatement does not apply to watercourse crossings - after installation of the first
pipeline, stabilisation work will commence so that the 25 metres to either side of the
watercourse will be reinstated within 48 hours.
For each crossing the contractor will minimise the environmental impact by installing
appropriate measures to prevent sediment entering the watercourse.
6 REINSTATEMENT OF LAND OTHER THAN
ROW
6.1 LAND AT CONSTRUCTION SUPPORT FACILITIES
Temporary construction facilities include worker camps, pipe dumps and hydrotest water
treatment areas. Reinstatement of the land will commence upon removal of individual facilities.
Disturbed areas will be reinstated to a condition as good, if not better than that that existed prior
to establishment of the facilities, and will be to the satisfaction of the owner/authority.
In environmentally sensitive areas, the original conditions and character will be restored as far
as practicable.
6.2 WASTE DISPOSAL SITES
The contractor will close, cap, and landscape all waste disposal sites prior to demobilisation,
unless otherwise agreed with the project. With the exception of waste soil/rock sites, this will be
in accordance with the relevant requirements of the European Community relating to the
management of waste disposal facilities. Bio-restoration will be undertaken as necessary to
ensure the site blends with the local environment. (See Section 10).
Sites that are used only for the disposal of excess soil and rock will be closed, capped and
landscaped Each site will be vegetated as necessary to meet the erosion control requirements
and to blend in with the local environment.
6.3 ROADS AND ACCESS TRACKS
Existing roads will be reinstated to their original condition or better following completion of
construction activities.
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
A-I-5
BTC PROJECT ESIA
GEORGIA
FINAL ESIA
New and upgraded roads or tracks and other project areas in Environmentally Sensitive Areas
will be removed and the land reinstated to its original condition, unless otherwise agreed
following consultation with all interested parties.
7 REINSTATEMENT PROCEDURES
The following subsections discuss activities that will take place prior to and during
reinstatement of the disturbed areas.
7.1 TOPSOIL REMOVAL AND STORAGE
Topsoil, containing the seed bank, is defined as the top layer of material on the land surface
capable of supporting plant growth. Maintenance of topsoil quality, particularly its structure and
the integrity of its seed bank, are vital to both bio-restoration and erosion control.
Principles for removal and storage include:
The width to be stripped of topsoil will be the working width required to construct and
install the BTC pipeline but excludes the area that will be used to store topsoil. The
contractor may apply for relaxation to this requirement where the ground is solid rock
(ie no soil at all) taking into consideration the local conditions, pre-entry agreements and
the need to satisfactorily reinstate the pipeline route. Any modification will be agreed
with the project prior to works being carried out
Where excavation is necessary, the depth of the topsoil will be established and up to
300mm of topsoil will be stripped and stored in a dedicated place. Topsoil below
300mm will only be removed if this is specifically required
Topsoil will be stored in a manner that minimizes its loss and or degradation.
Degradation of structure occurs when over-compacted by vehicles, while fertility and
viability degradation occur when the topsoil is mixed with less fertile subsoil
Topsoil stacks will be placed to ensure that they:
Are stable, and not subject to slumping or washout
Drain freely and do not pond water
Provide reasonable access across the ROW
Maintain aerobic conditions
Stockpiles will be seeded where necessary to prevent weed growth
Topsoil will not be used for bedding or padding material, or for trench breakers/plugs
During handling, damage to topsoil structure will be avoided
Topsoil handling under rainy conditions will be avoided for soils with a high clay
content or specifically wet conditions
7.2 SUBSOIL REMOVAL AND STORAGE
Subsoil will be managed so that it does not contribute directly or indirectly to excessive erosion.
The following principles apply for removal and storage of sub-soil:
Subsoil will be excavated from the pipe trench and, in some cases, additionally from
cutting of benches on sides of slopes
Subsoil will be stored separately from topsoil, and will not be mixed
Subsoil will be returned to the excavated area, as far as practicable
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
A-I-6
BTC PROJECT ESIA
GEORGIA
FINAL ESIA
Subsoil which cannot be re-used, ie returned to the trench or corridor ROW, will be
placed in stockpiles
Stockpiles will be stable from collapse and drain freely
Drainage will be provided to manage appropriately the water and sediment loads
running off the subsoil stockpiles (eg gaps, flumes, etc)
Disposal of excess subsoil is discussed in the section 7.3
7.3 TRENCH EXCAVATION AND PIPELINE PADDING
The creation of excess excavated material will be minimized as far as practicable. Excess
material will be recovered and re-used to the greatest extent possible.
Fillmaterials will not be imported unless it is demonstrated that:
such fill is technically necessary and/or
online processing is technically infeasible or uneconomic; and that
suitable backfill cannot be provided by excavation techniques
Priorities for managing excess material are as follows:
1st priority: ROW Re-use:
Where generated spoil is suitable for use as a construction material it will be re-used on the
ROW for project infrastructure works materials; stability, erosion control, worker camps, AGIs,
etc.
2nd priority: ROW / Project-Area Disposal:
Use in project areas eg simulation of rock streams / glaciers in adjacent areas, hillside
contour blending
Localised increase in finished surface height of ROW
Increase in finished surface height of AGIs
All disposal/re-use in the project areas will be done without environmental impact to off-project
areas.
3rd priority Off ROW Re-use:
Transfer to third Party for re-use purposes as raw or semi-finished materials, eg crushed
andesite that may be suitable for road construction materials or for rail ballast.
4th priority: Off ROW Disposal:
Potential disposal sites have been identified, and an operating permit will be required in case
they are selected by the contractor. The contractor will plan, develop, operate and reinstate those
sites to international standards. Alternatively, the contractor may propose other sites for
approval. The contractor will be responsible for the technical and environmental assessment of
such sites and for obtaining regulatory approval for alternative sites.
In principle, excess material will not be disposed of in the following area:
in environmentally sensitive areas (except with prior project approval)
in areas adjacent to special agricultural sections
in watercourses or valley bottoms
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
A-I-7
BTC PROJECT ESIA
GEORGIA
FINAL ESIA
in windrows over the pipe
on side slopes below benches or ridge cuttings where the side slope exceeds 45°
where they will potentially interrupt concentrated overland flow
in such a way as to cause unacceptable landscape (visual) impact
on any open area where the slope exceeds 30°
Sites for the disposal of excess excavated material will, in general, comply with the
requirements for ‘Inert’ waste disposal sites. However, provided a number of conditions are
met, a reduced specification for the design of the site may apply. Conditions include the
requirement that the site be stable and appropriately drained, with only natural materials
deposited; and the transport vehicles do not transport other type of waste.
7.4 REINSTATEMENT OF SOILS
7.4.1 Reinstatement of subsoil
Two situations are considered: standard reinstatement and special reinstatement.
Standard reinstatement
On return of the subsoil to the trench or ROW, the subsoil will be compacted to levels
similar to the adjacent undisturbed area. The depth of subsoil after settlement will not be
above the level of the surrounding ground. After the subsoil has been returned and the
land levelled, the subsoil will be ripped to a depth of 350-400mm, rendered to a loose
and workable condition and contoured in keeping with the adjacent undisturbed ground.
Special Area reinstatement
Special Area Reinstatement is applied where it has been necessary to cut a bench into
the hillside in order to lay the pipe and the intention is to restore the original contours by
filling-in the bench, thereby removing any visual impact in the landscape. Locations
where this is required relate to defined environmentally sensitive areas and special
agricultural areas.
Upon completion of reinstatement of subsoil, disturbed areas will be inspected jointly by
the contractor and the project for slope stability, relief, topographic diversity, acceptable
surface water drainage capabilities, and compaction.
7.4.2 Reinstatement of topsoil
Topsoil will not be mixed with spoil material during replacement. Only topsoil (and equivalent
materials as permitted by this specification) will be re-spread over the surface. Topsoil will not
be used for bedding material in the trench, and topsoil from unstripped/undisturbed areas will
not be used to cover adjacent disturbances. Topsoil will not be handled under wet conditions or
at times when the ground or topsoil are frozen.
All disturbed areas will be subject to final grading; however, measures will be taken prior to
seeding to ensure disturbed areas remain in sufficiently rough condition to protect the stability
of topsoil after its re-distribution and to promote vegetation growth.
APPENDIX A I - REINSTATEMENT SUMMARY PLAN
NOVEMBER 2002
A-I-8
Description:Reinstatement of project areas disturbed by pipeline construction activities (eg Improved likelihood of maintaining pipeline integrity against inclement sympathetic to the natural landscape will be used, including brown, grey and green Pigging station G1 BTC, south-east of Tsikhisjvari (KP 182).