Table Of ContentRapport
Eksamen BIM-tekniker 2015
BIM-I, Fagskolen Oslo Akershus
Stian Scheflo
Mai 2015
Eksamen BIM-tekniker 2015
INNHOLDSFORTEGNELSE
1 Oppgavetekst ...................................................................................................................................... 4
2 Introduksjon .......................................................................................................................................... 6
2.1 Sammendrag ............................................................................................................................... 6
2.2 Gruppe .......................................................................................................................................... 7
2.3 Prosjektbeskrivelse ....................................................................................................................... 7
3 Forbredelser/planlegging .................................................................................................................. 8
3.1 Samarbeidsavtale ....................................................................................................................... 8
3.2 Gjennomføringsplan ................................................................................................................... 8
3.3 Problemstilling .............................................................................................................................. 8
3.3.1 Forklart ....................................................................................................................................... 8
3.4 Fremdriftsplan .............................................................................................................................. 9
3.4.1 Teamup ..................................................................................................................................... 9
3.4.2 MS Project/Synchro ................................................................................................................ 9
3.5 Plan for backup ........................................................................................................................... 9
3.5.1 Oppsett av automatisk backup ........................................................................................ 10
3.6 Kommunikasjon ......................................................................................................................... 10
3.7 Filutveksling ................................................................................................................................. 11
3.8 Mappestruktur ........................................................................................................................... 11
3.9 BIMCollab ................................................................................................................................... 12
3.10 Nettside/mail .............................................................................................................................. 12
4 Egen Planlegging .............................................................................................................................. 13
4.1 Dokumenter/vedlegg vedlagt eksamensoppgave .......................................................... 13
4.2 Prosjekt Informasjon på nett ................................................................................................... 13
4.3 Ventilasjon .................................................................................................................................. 14
4.3.1 Byggforsk ................................................................................................................................ 15
4.3.2 Retningslinjer for min modellering ...................................................................................... 16
4.3.3 Kontakt med Eiker Eiendomsutvikling: .............................................................................. 16
4.4 Fremdriftsplan ............................................................................................................................ 17
5 Logg ..................................................................................................................................................... 18
5.1 Georeferering ............................................................................................................................ 18
5.1.1 2.A Lokalt nullpunkt til NTM koordinater ............................................................................ 18
5.1.2 Etasje DWG riktig koordinert ............................................................................................... 19
1
Stian Scheflo
Eksamen BIM-tekniker 2015
5.1.3 Sjekke koordinater opp mot kartverket ............................................................................ 21
5.2 Oppstart i Revit .......................................................................................................................... 23
5.3 Landskap .................................................................................................................................... 23
5.4 2.B) Ukoordinert modell ............................................................................................................ 24
5.5 Modellering av Ventilasjon ...................................................................................................... 27
5.5.1 Utstyr tilgjengelig ................................................................................................................... 28
5.5.2 Revit family Tilluftsventil ........................................................................................................ 28
5.5.3 Hensyn føringsveier ............................................................................................................... 29
5.5.4 Anleggene utformes ............................................................................................................ 29
5.5.5 Automatisk dimensjonering av rør ..................................................................................... 29
5.5.6 IFC fra Archicad som underlag .......................................................................................... 31
5.5.7 Utfordring kobling av rør ...................................................................................................... 32
5.5.8 Duplikat objekter ................................................................................................................... 33
5.5.9 Rydding, Berikelse, informasjon og objekter .................................................................... 34
5.5.10 Ekstern utfordring .............................................................................................................. 38
5.5.11 IFC export ........................................................................................................................... 39
5.5.12 Egenkontroll i modellsjekker ............................................................................................ 41
5.6 Sammenstilling av modeller/møter ....................................................................................... 44
5.6.1 Første ICE møte/Oppstartsmøte ........................................................................................ 44
5.6.2 Andre ICE møte ..................................................................................................................... 44
5.6.3 Tredje ICE møte ..................................................................................................................... 45
5.7 4D simulering .............................................................................................................................. 45
5.7.1 Fremdriftsplan ........................................................................................................................ 45
5.7.2 Kontakt med bedrifter ......................................................................................................... 46
5.7.3 Synchro ................................................................................................................................... 48
5.7.4 Import av fremdriftsplan ...................................................................................................... 48
5.7.5 Importere IFC ......................................................................................................................... 50
5.7.6 Kobling fremdriftsplan og objekter .................................................................................... 51
5.7.7 Oppdatere fremdriftsplan ................................................................................................... 55
5.7.8 Ressursimport og tildeling .................................................................................................... 56
5.7.9 Oppdatere modeller ............................................................................................................ 57
5.7.10 Splitte objekter ................................................................................................................... 57
5.7.11 Utskrift/Eksport av informasjon ........................................................................................ 58
5.7.12 Eksport av film/bilder ........................................................................................................ 59
5.7.13 Eksport av 3D ..................................................................................................................... 61
5.8 Tegninger .................................................................................................................................... 62
2
Stian Scheflo
Eksamen BIM-tekniker 2015
5.8.1 Legends .................................................................................................................................. 62
5.8.2 Tags .......................................................................................................................................... 62
5.9 Mengdelister .............................................................................................................................. 62
6 Oppsummering .................................................................................................................................. 63
7 Konklusjon ........................................................................................................................................... 64
8 Egenvurdering .................................................................................................................................... 65
9 Hjelpemidler ....................................................................................................................................... 65
9.1 Programmer ............................................................................................................................... 66
9.2 Nettsider ...................................................................................................................................... 67
9.3 Personer ...................................................................................................................................... 67
10 Kildehenvisning .................................................................................................................................. 68
11 Vedlegg .............................................................................................................................................. 69
11.1 Samarbeidsavtale ..................................................................................................................... 69
11.2 Gjennomføringsplan ................................................................................................................. 69
11.3 Fremdriftsplan ............................................................................................................................ 69
11.4 Møteinnkalling ........................................................................................................................... 69
11.4.1 18.mai 2015 ........................................................................................................................ 69
11.4.2 21.mai 2015 ........................................................................................................................ 69
11.4.3 26.mai 2015 ........................................................................................................................ 69
11.5 Møtereferat ................................................................................................................................ 69
11.5.1 18.mai 2015 ........................................................................................................................ 69
11.5.2 21.mai 2015 ........................................................................................................................ 69
11.5.3 26.mai 2015 ........................................................................................................................ 69
11.6 Synchro fremdriftsplan ............................................................................................................. 69
11.7 ICE møte/BCF rapport .............................................................................................................. 69
11.7.1 21.05.2015 ........................................................................................................................... 69
11.7.2 26.05.2015 ........................................................................................................................... 69
11.8 Tidligere innsendt fremdriftsplan, problemstilling og prosjektbeskrivelse ....................... 69
11.9 Utdrag funksjonsbeskrivelse..................................................................................................... 69
11.10 Tegninger ................................................................................................................................ 69
11.10.1 2015-03.001 Oversikt mengder aktivitet ....................................................................... 69
11.10.2 2015-03.002 Aktivitet ID kjeller ......................................................................................... 69
11.10.3 2015-03.003 Luftmengde kjeller ...................................................................................... 69
11.10.4 2015-03.004 Parkeringskjeller lufthastighet ................................................................... 69
11.10.5 2015-03.005 Aktivitet ID teknisk og 1 etasje .................................................................. 69
11.10.6 2015-03.006 Leilighet A..................................................................................................... 69
3
Stian Scheflo
Eksamen BIM-tekniker 2015
1 OPPGAVETEKST
Eksamen BIM-tekniker 2015 Fagskolen Oslo
Akershus
Eksamensperiode: Mandag 18.mai – fredag 29.mai, framføring 3.-5.juni.
Tema for BIM-K og BIM-I:
«Berikelse, høsting og bearbeiding av data».
Det foreligger underlagsfiler som skal benyttes.
Lag en problemstilling for oppgaven din innenfor temaet. Bruk
underlagstegningene som et utgangspunkt og ta gjerne egne valg i forhold til
utforming. Husk at problemstillingen skal være en rød tråd gjennom hele
arbeidet. Rapporten, framføringa og vedlagte filer danner grunnlaget for
vurderinga.
Vurderingskriterier:
1. Problemstilling
Rapportens utforming samt løsningsforslag til problemstillingen og refleksjoner
rundt eget arbeid.
2. Georeferering
a. Før modellering: Prosjektet skal
X East Y North
georefereres.
66910,000 1197160,000
Lokalt nullpunkt settes til koordinaten i NTM:
Kart og aksenett er vedlagt.
b. Etter modellering: I mappen Ukoordinert ligger det en IFC-fil som ikke er
plassert riktig.
Flytt denne i Solibri slik at den ligger rett i forhold til georefereringen i punkt 1.a
Oppgi ∆X, ∆Y, ∆Rotation og Pivot Point brukt i flyttingen.
Når denne modellen er sammenstilt med ARK har du muligheten til å oppdage en
åpenbar feil. Hvilken?
3. Modell, kvalitetssikring og tegninger
Kontroll og verifisering av data, løsninger og resultater. Modellens kompleksitet
og bruk av effektive modelleringsteknikker. Tegninger som forholder seg til
problemstillingen med målsetting og tekst.
4
Stian Scheflo
Eksamen BIM-tekniker 2015
4. Samhandling og informasjonsflyt
Det oppfordres til tverrfaglig samarbeid og simulering av samhandlingsprosesser
man kan møte i reelle byggeprosjekter.
Leveranse:
Det skal leveres to papirrapporter.
Modellfilene og andre filer enn rapporten leveres på Fronter i en zippa
pakke.
Sammen med den zippa pakken leveres et txt-dokument som beskriver
hva som er levert i den zippa pakken og hvem som står for arbeidet.
Navngivingsregel for Fronterinnleveringer: ”Ditt navn – beskrivelse”.
Tidsfrister:
• Fremdriftsplan + prosjektbeskrivelse (levert på papir og Fronter): Tirsdag
19.mai kl.15:00
• Rapport (PDF og papir), samt zippa mappe med txt.fil: Fredag 29.mai kl 13:15.
• Framføring skjer onsdag 3.- fredag 5.juni fra kl.08:00. Hver student får ca 20
minutter.
Rekkefølgen på framføring blir trukket fredag 29.mai før kl 15 og lagt ut på
Fronter under mappa Prosjekter – Eksamen. Det skal framføres individuelt.
Rapporten bør inneholde:
1. Forside
2. Innholdsfortegnelse
3. Dette arket
4. Fremdriftsplan(er) med problemstilling
5. Sammendrag med konklusjon
6. Beskrivelse av arbeidet med bilder og fotografier. Legg vekt på å
verifisere resultatene.
7. Oppsummering av prosjektet, svar på problemstillingen; refleksjoner!
8. Kildehenvisning / ”Takk til…”
9. Egenvurdering/gruppevurdering (svar på pkt 1-4 over)
10. Vedlegg (bl.a. tegninger)
Lykke til!
5
Stian Scheflo
Eksamen BIM-tekniker 2015
2 INTRODUKSJON
Dette er rapporten som ble utformet på BIM-I linjen ved Fagskolen i Oslo eksamensperioden
18-29 mai 2015. Den har blitt utformet for å gi et klart bilde av arbeidet som ble utført i
eksamensperioden. Rekkefølgen av innholdet representerer i store deler også rekkefølgen
arbeidet ble utført. Det er ikke meningen at rapporten skal kunne bli brukt som bruksanvisning
eller steg for steg forklaring, men det kan forekomme der det faller naturlig inn i arbeidstypen
utført. Leser av denne rapporten bør også ha godt innsyn i ord, utrykk og programmer som
blir benyttet i sammenheng med BIM.
2.1 SAMMENDRAG
I Hokksund i Drammen har det lenge vært planer om å
bygge leilighetskompleks i Støagata. Dette har vært en
problematisk prosess for Øvre Eiker Eiendomsutvikling
som sitter som byggherre, men selv om dette prosjektet
ikke er i gang på ordentlig stopper ikke det oss i BIM å
modellere prosjektet digitalt.
BIM linjene har fått underlag fra Støahagen prosjektet i
sammenheng med eksamen 2015. Jeg har foretatt
meg modellering av ventilasjon i deler av byggene,
selv om jeg egentlig har fagbrev som elektriker.
I dette prosjektet har jeg sett ekstra mye på muligheter rundt hvordan modeller og
fremdriftsplaner kan kobles sammen for å skape 4D. Dette er et tema som jeg mener er viktig
for å enkelt og effektivt kunne ta mer i bruk 4D. Samt kunne dra nytte av 4D til noe mer en
visualisering som det blir mye brukt til i dag.
Rapporten har ikke fokus på korrekt modellering av ventilasjon, men heller pre-aksepterte
løsninger har blitt brukt som veiledning grunnet lite fagkunnskaper rundt ventilasjon. Grunnen
til at jeg har valgt ventilasjon i dette prosjektet er fordi det ofte er plasskrevende i bygg og
krever mer hensyn i forhold til koordinering. Valget av ventilasjon ble også gjort fordi det er
mer egnet for 4D simulering enn elektro.
6
Stian Scheflo
Eksamen BIM-tekniker 2015
2.2 GRUPPE
Personene i BIMgruppen under eksamensprosjektet har vært:
Tilleggsroller:
Martin: møteleder og referent.
Thomas: BIM-koordinator og BCF sjef
Jeg har hatt ansvar for oppsett av nettside/mail og prosjekthotell.
2.3 PROSJEKTBESKRIVELSE
Å kunne jobbe gjennom store prosjekter med
fremdriftsplaner og modeller sammensveiset til enhver tid,
kan være utrolig nyttig for mange deler av prosjektets
aktører. Alt fra risiko på arbeidsplassen til mengder i
prosjektaktiviteter og mye mer kan i teorien bli håndtert
på et veldig visuelt nivå. For eksempel når en
vareleveranse ikke lenger er en linje på et ark, men et
faktisk objekt på en simulert digital byggeplass.
Det høres fint og flott ut, men bak det hele er kanskje det
elementære ikke godt nok sett på.
Hvordan skal modeller og fremdriftsplaner bli koblet
kontinuerlig gjennom prosjekttiden? Da med alle tillegg og endringer som oppstår slik at
simuleringen skal forbli oppdatert og kunne bli stolt på?
Jeg har modellert ventilasjon i Revit 2015 og sett på programmet Synchro 5 som kan fremstille
4D med både fremdriftsplaner laget i Microsoft Project og IFC modeller.
Dette prosjektet tar for seg utfordringer og løsningsforslag i forhold til temaene:
Modellering og informasjonshåndtering i Revit
Arbeid med DWG og georeferering i Autocad
Flytting av 0 punkt i IFC i SimpleBim
Kontroll av modell og informasjon i Solibri
Oppbygning av fremdriftsplaner
Kobling av IFC modell mot aktiviteter i fremdriftsplan i Synchro
Importere/eksportere data i Synchro
7
Stian Scheflo
Eksamen BIM-tekniker 2015
3 FORBREDELSER/PLANLEGGING
3.1 SAMARBEIDSAVTALE
Samarbeidsavtalen finnes i vedlegg
3.2 GJENNOMFØRINGSPLAN
Gjennomføringsplan finnes i vedlegg
3.3 PROBLEMSTILLING
«Hvordan koble modell og fremdriftsplan sammen for å skape 4D simulering?»
3.3.1 FORKLART
Meningen med denne problemstillingen er å få et innsyn i mulighetene rundt fremstilling av
en 4D modell, helst med åpne formater, samt lære litt om programmene Synchro og
Microsoft Project i løpet av eksamenstiden.
Tanken bak denne problemstillingen er; gjennom skoleåret har jeg sett på mange (etter min
mening) viktige problemstillinger som BIM kan bidra med, men som ikke er blitt tatt godt i bruk
i praksis mange steder. Og denne problemstillingen er sånn sett ikke annerledes enn tidligere.
4D kan bidra med viktige simuleringer av et prosjekt som kan øke produktiviteten,
samarbeidet mellom aktører og minske risiko, kostnader og konflikter.
Målet er å kunne effektivt kunne ha en fremdriftsplan og modell som fungerer sammen for å
simulere fremdriften i et prosjekt. Her skal man kunne forutse utfordringer og kunne
endre/velge nye løsninger basert på data fra både modell og fremdriftsplan.
Utfordringen med denne problemstillingen er at jeg har lite erfaring med fremdriftsplaner og
programmer som håndterer disse. Det kan også bli en utfordring når oppdaterte/nye
modeller/fremdriftsplaner kommer og de skal kobles/synkroniseres «enkelt» med hverandre.
Hvor omfattende BIM og fremdriftsplaner er i prosjekter er veldig varierende, derfor kan
fremgangsmetoden jeg velger kanskje kun fungere i noen enkelte situasjoner.
8
Stian Scheflo
Eksamen BIM-tekniker 2015
3.4 FREMDRIFTSPLAN
3.4.1 TEAMUP
Som en fremdriftsplan på gruppenivå ble den nettbaserte kalenderen TeamUp benyttet.
Dette er en gratis tjeneste som gir muligheten til å lage en kalendere for hver deltager og
sammenstille kalenderen til alle i gruppen.
I tillegg har man mulighet til å få mail eller en push melding(iCalender) når endringer har blitt
gjort i kalenderen og på denne måten er det lett å ha en fremdriftsplan som blir fulgt og som
er oppdatert til enhver tid.
Fremdriftsplanen finnes i vedlegg
3.4.2 MS PROJECT/SYNCHRO
Ved siden av den fremdriftsplanen på personnivå har det blitt laget en fremdriftsplan for
«byggeprosjektet». Dette skal illustrere «ekte» byggetid, for at vi ikke er nødt til å lage hele
bygget på to uker i fremdriftsplanen. Denne fremdriftsplanen ble laget kun for min egen
problemstilling.
Mer om bruk av fremdriftsplanen
3.5 PLAN FOR BACKUP
I dette prosjektet har 4 veis backup blitt
benyttet.
Intern sekundær harddisk
Ekstern harddisk
Skylagring(OneDrive)
Prosjekthotell(Byggeweb)
9
Stian Scheflo
Description:IFC import (Archicad connection). Her ser jeg fort at det har blitt gjort noe rart når modellen har blitt georeferert i Archicad. Jeg flyttet base point til 0 og lagret modellen (bilde til høyre). Jeg ble nysgjerrig på om ARK modellene fra min gruppe hadde det samme problemet i Revit. Her gikk i